METHOD STATEMENT OF FABRICATION OF HEAVY SCH. PIPING
INDEX
1.0
OBJECTIVE.
2.0
EXECUTION
OF WORK.
3.0
WPS
AND PRQ.
4.0
RELEVANT STANDARD.
5.0
MATERIALS.
6.0
FILLER
WIRE.
7.0
CONSUMABLE.
8.0
TOOLS
AND TACKLES.
9.0
EDGE
PREPARATION.
10.0
FIT
UP, ALINGMENT AND WELDING.
11.0
HEAT
TREATMENT.
12.0
NON
DESTRUCTIVE TESTING.
13.0
BLASTING
AND PAINTING.
14.0
FINAL
INSPECTION AND DISPATCH.
-------------------------------------------------------------------------------------------------------------------------------
1.0
OBJECTIVE
TO EXECUTE THE
WORK AND PROVIDE SAFE, COMPETENT,
PROFESSIONAL AND QUALITY SERVICE WITHIN THE TIME SCHEDULE.
CLIENT’S REQUIREMENT
TO CARRY FABRICATION, STRESS RELIVING,
RADIOGRAPHY AND BLASTING & PAINTING OF HEAVEY SCHEDULE PRESSURE PIPING.
-
SAFETY OF
PERSONNEL & SAFE WORK PRACTICE.
-
GOOD
ENGINEERING PRACTICE
-
ENSURE
QUALITY OF WORK
-
ADHERE TO
TIME SCHEDULE
-
MOBILIZATION
OF RESOURCES ON TIME
2.0
EXECUTION OF WORK:-
2.1
WORK SHOP
THE SITE
SHALL BE MOBILIZED WITHIN STIPULATED PERIOD THE AWARD OF LOI / WORK ORDER.
3.0
WPS & PQR
3.1
THE WELDING
PROCEDURE SPECIFICATION (WPS) FOR
PIPING SHALL BE SUBMITTED TO CLIENT FOR REVIEW AND APPROVAL.
3.2
ON APPROVAL
OF WPS, THE WELDING PROCEDURE QUALIFICATION (PQR) AND SUBSEQUENTLY WELDER’S QUALIFICATION SHALL BE CARRIED OUT AT WORK SHOP.
4.0
RELEVANT STANDRAD
ASME 31.3
5.0
MATERIALS
5.1
CONTRACTOR
SHALL ARRANGE TO RECEIVED AND STORE ALL FREE ISSUE MATERIALS.
5.2
PIPES AND
FITTINGS USED IN THIS PARTICULAR PIPING SHALL BE AS SPECIFIED IN PIPING
SPECIFICATION.
5.3
CONTRACTOR
SHALL VISUALLY INSPECT MATERIALS BEING COLLECTED AND IMMEDIATELY BRING IN TO THE
NOTICE CLIENT ANY DISCREPANCY OR SHORT FALL NOTICED
5.4
CONTRACTOR
WILL DEPLOY ONE MOBILE CRANE WITH SUFFICIENT MAN POWER AND LIFTING TOOLS FOR
SAFE HANDLING OF MATERIALS AS ILLUSTRATED IN SKETCH.

6.0
FILLER WIRE
- CONTRACTOR SHALL ARRANGE TO SUPPLY FILLER WIRE REQUIRED FOR THE JOB.
- CONTRACTOR SHALL ENSURE THAT APPROVED BRAND OF FILLER WIRE IS USED.
- CONTRACTOR SHALL PRODUCE THE BATCH CERTIFICATE FOR EVERY BATCH OF FILLER WIRE.
7.0
CONSUMABLES:-
- CONTRACTOR SHALL ARRANGE AND SUPPLY ALL CONSUMABLE
- CONTRACTOR SHALL ENSURE THAT ALL REGULATOR, HOSES ETC. USED ARE REPUTED BRAND.
- PURITY OF ARGON SHALL BE 99.995% WHEN USED FOR SHIELDING AND PURGING.
- FLOW RATE OF PURGING GAS SHOULD BE ESTABLISH DURING PROCEDURE QUALIFICATION RECORD TEST.
8.0
TOOLS AND TACKLES.
- CONTRACTOR SHALL PROVIDE ALL NECESSARY TOOLS AND TACKLES REQUIRED FOR THE JOB. LIST OF TOOLS AND TACKLES ARE MAILED TO CLIENT.
- ALL GAUGES USED ARE TO BE TESTED SHALL BE CALIBRATED AND TEST CERTIFICATES MADE AVAILABLE FOR VERIFICATION.
9.0
EDGE PREPARATION
- EDGE SHALL BE PREPARED BY BEVELING MACHINE.
- EDGE SHALL BE CLEANED TO REMOVE ANY DUST, DIRT OR RUST WHICH MAY BE PRESENT PRIOR TO FIT UP.
10.0 FIT
UP,ALINGMENT AND WELDING
1. ALIGNMENT
AND FIT UP OF INDIVIDUAL PIPING COMPONENT IS ESSENTIAL TO OBTAIN A GOOD JOINT
THERE FOR LOT OF CARE MUST BE TAKEN DURING FIT
UP.
2.
CONTRACTOR
SHALL BE RESPONSIBLE FOR ACCURACY OF FABRICATION. CONTRACTOR SHALL REVIEW THE
DRAWING AND IN CASE ANY ARROW OR OMISSION IS IDENTIFIED THE SAME SHALL BE
BROUGHT INTO THE NOTICE OF CLIENT
3.
COMPONENTS
TO BE ALIGNED SHALL BE SPACED AS PER APPLICABLE CODE.
4.
WIRE
SPACERS SHALL BE USED TO OBTAIN PROPER ROOT GAP, HOWEVER AFTER TACK WELDING
THERE SHALL BE REMOVED.
5.
ALL TACK
WELDER DEPLOYED SHALL BE TESTED AND QUALIFIED. ALL TACK WELD SHALL BE DONE
UTMOST CARE SINCE THIS WORLD FORM A PART IF FINAL WELDING.
6.
TACKS SHALL
BE EQUALLY SPACED. THE MINIMUM NUMBER OF TRACKS FOR VARIOUS SIZE OF PIPES SHALL
BE AS FOLLOWS
6.1 PIPE SIZE No. OF TACKS
a) 3’’ DIAMETER AND BELOW 2
b) BETWEEN 3 AND 12’’ DIAMETER 4
c) ABOVE 12’’ DIAMETER 6
7.
ALL
DEFECTIVE FIT UP OF TACK WELDS WHICH ARE REJECTED BY THE CLIENT SHALL BE
REDONE.
8.
PRIOR TO
WELDING FIT UP SHALL BE JOINTLY INSPECTED BY CONTRACTOR, CLIENT AND CONSULTANT
AND RELEASE FOR WELDING
9.
WELDER
QUALIFICATION AS PER THE SPECIFICATION SHALL BE CARRIED OUT PRIOR TO
COMMENCEMENT OF WELDING.
10. ONLY QUALIFIED TACK WELDERS OR WELDERS ARE ALLOWED
TO WORK ON THE JOB
11. CONTRACTOR SHALL MAINTAIN THE FOLLOWING DOCUMENTS FOR
THE WELDERS.
a)
WELDING
PROCEDURE SPECIFICATION.
b)
PROCEDURE
QUALIFICATION RECORD.
c)
WELDER IDENTIFICATION CARD.
12. ALL DOCUMENTS SUCH AS DAILY FIT UP AND WELDING
REPORT SHALL BE MAINTAINED BY THE CONTRACTOR. CLIENT OF CONSULTANT SHALL BE
FREE TO INSPECT AND RECORD HIS OBSERVATION ON THESE DOCUMENTS
13. ABOVE ACTIVITIES IS FURTHER ILLUSTRATED IN THE SKETCH.

![]() |
| Add caption |
11.0 HEAT TREATMENT (STRESS RELIVING)
11.1
HEAT
TREATMENT OF CARBON STEEL IS NOT REQUIRED, UNLESS SPECIFICALLY STATED IN THE
DRAWINGS
11.2
CARBON
STEEL MATERIALS HAVING CARBON CONTENT 0.35% MAXIMUM AND WALL THICKNESS LESS
THEN 19 MM DO NOT REQUIRE TO BE HEAT TREATED.
11.3
CARBON
STEEL MATERIALS HAVING CARBON CONTENT 0.35% MAXIMUM AND WALL THICKNESS 19 MM OR
ABOVE NEED TO BE STRESS RELIVED.
11.4
CARBON
STEEL MATERIALS HAVING CARBON CONTENT ABOVE 0.35% MAXIMUM IRRESPECTIVE OF WALL
THICKNESS REQUIRED TO BE HEAT TREATED.
11.5
THE JOINT
SHALL BE WRAPPED IN ASBESTOS OR MINERAL WOOL TO A DISTANCE OF 150 MM ON BOTH
SIDE OF WELD JOINT DURING HEATING OR COOLING.
11.6
STRESS
RELIVING CAN BE DONE BY DEPLOYING A FURNACE OR BY USING ELECTRIC RESISTANCE OR
INDUCTION HEATING EQUIPMENT.
11.7
THE
TEMPERATURE OF THE JOINT BEING STRESS RELIVE SHALL BE RECORDED BY USING
THERMOCOUPLES AND RECORDER. THE MINIMUM NUMBER OF THERMOCOUPLES TO BE PROVIDED
PER JOINT SHALL BE AS STATED BELOW.
JOINT SIZE NO. OF THERMOCOUPLES
a) UPTO 6 ‘’ 1
b) UPTO 10’’ 2
c) FOR 12’’ AND ABOVE 3
11.8
AFTER
COMPLETION OF STRESS REVELING HARDNESS TEST SHALL BE CONDUCTED ON THE JOINTS
11.9
ALL NECESSARY DOCUMENTATION SHALL BE
PREPARED AND MAINTAINED BY THE CONTRACTOR AND THE SAME WILL BE FORWARDED TO
CONSULTANT FOR REVIEW AND APPROVAL.

12.0 NON DESTRUCTIVE TESTING
12.1 RELEVANT STANDARD
1.0 ASME SECTION V
12.2 VISUAL EXAMINATION
12.2.1
WELDS JOINTS SHALL BE VISUALLY
EXAMINED AND RELEASED FOR RADIOGRAPHY
12.3 HARDNESS TEST EXAMINATION
12.3.1
HARDNESS TEST SHALL BE CARRIED OUT AS
SPECIFIED IN THE PIPING SPECIFICATION INDEX / DRAWINGS OR AS PER THE
INSTRUCTION OF CONSULTANT ENGINEER.
12.4 RADIOGRAPHIC EXAMINATION
12.4.1
PROCEDURE FOR RADIOGRAPHY EXAMINATION
TO BE ADOPTED WILL HAVE TO BE FURNISHED BY THE CONTRACTOR TO THE CONSULTANT AND
APPROVAL OBTAINED.
12.4.2
CONTRACTOR SHALL FURNISH THE NAMES AND BIO DATA OF THE RADIO GRAPHIC CONTRACTOR. NO AGENCY OR CONTRACTOR SHALL BE
DEPLOYED WITHOUT THE APPROVAL OF CONSULTANT. RADIOGRAPHER SHOULD HAVE MINIMUM
LEVEL II QUALIFICATION.
12.4.3
THE RADIOGRAPHIC TECHNIQUE AND
PROCEDURE ADOPTED SHALL CONFIRM TO THE REQUIREMENTS OF ASME SECTION V.
12.4.4
THE ACCEPTABLE LIMITS OF DEFECTS AND
REMOVAL OF DEFECTS SHALL BE AS THE RELEVANT CODE OF FABRICATION.
12.4.5
ALL STATUTORY, SAFETY REQUIREMENT
WHILE HANDLING X-RAY SOURCE SHALL BE FOLLOWED BY THE CONTRACTOR.
12.4.6
PERCENTAGE OF RADIOGRAPHY SHALL BE AS
STATED IN THE PIPING SPECIFICATION OR DRAWINGS.
12.4.7
CONTRACTOR SHALL RADIOGRAPHY THE JOINTS
SELECTED BY THE CONSULTANT INSPECTOR.
12.4.8
AFTER RADIOGRAPHY THE CONTRACTOR SHALL
FURNISH ALL THE RADIOGRAPHY TO THE CONSULTANT ENGINEER AFTER PROCESSING ALONG
WITH HIS OBSERVATION.
12.4.9
ALL NECESSARY DOCUMENTATION SHALL BE
PREPARED AND MAINTAINED BY THE CONTRACTOR AND THE SAME WILL BE FORWARDED TO
CONSULTANT FOR REVIEW AND APPROVAL.
13.0 BLASTING AND PAINTING
13.1
BLASTING YARD SHALL BE BUILT UP WITH
MACHINERY SUCH AS AIR COMPRESSOR, SPRAY PAINTING EQUIPMENT, HOPPER, HOSES AND
COPPER SLAG FOR BLASTING AND PRIMER APPLICATION.
13.2
BARE PIPES RECEIVED FROM CLIENT WILL
BE BLASTED AND PRIMED USING COPPER SLAG OR SAND AND ZINC PHOSPHATE PRIMER (RED OXIDE)
TO THE REQUIRED DFT OF 30 MICRON PRIOR TO WELDING OF FLANGES.
13.3
SLIP ON OR WELD NECK FLANGES WILL BE
WELDED ON THE PRIMED PIPE.
13.4
FINAL EPOXY PAINT WILL BE APPLIED ON FINISH SPOOLS.

14.0 FINAL
INSPECTION AND DESPATCH OF SPOOLS
14.1
FINISH
SPOOLS ARE INSPECTED AND DISPATCH TO ERECTION SITE.

Hi, it was very informative post.Thank you for sharing with us. I think nowadays middle-east companies like alboom groups helping customers to procure all necessary equipment’s and materials for Fabrication and erection of piping with the most competitive and reliable materials in terms of cost and quality.
ReplyDeleteBuilding Materials Shops in Bahrain | Plywood Dealers in Bahrain
I am very glad to read this nice article. I am happy that you made this concept very clear in front of people and to be very frank this is useful information too. Keep it up.
ReplyDeletePiping Fabrication in Accra Ghana
Dashinspectorate
I see your point, and I really enjoy your opinion. It goes without saying I also love the design of your website, extremely artistic. Later. https://westasianetwork.com/ashford-formula-riyadh.php
ReplyDeleteThis is truly one of the most amazing articles I have ever read. I hope it helps a lot for everyone. Thanks a lot for these awesome posts and please keep updated like this excellent article. Incoloy 825 Fasteners
ReplyDeleteThis is a great article with many informative sources. I appreciate your work its really helpful for all. Check out our website 304L Stainless steel Round Bar for more information on Stanley Alloys!
ReplyDeleteThis comment has been removed by the author.
ReplyDeleteThe author's writing was appealing and engrossing from the first to the last paragraph.
ReplyDeleteUNS N08904 Plates
I appreciate how the author looks into the issue's historical backdrop since it helped me comprehend how the subject has changed.
ReplyDeleteHastelloy C276 Bolt
Anyone wanting to learn more about the topic can use this page as an excellent place to start because it gives a thorough summary.
ReplyDeleteDuplex Steel 2205 Sheets
This article's wording is straightforward and concise. It is admirable how the author can convey intricate concepts in such a simple way.
ReplyDelete316Ti Stainless Steel Foil
Nice articles and your information valuable and good articles thank for the sharing information COPPER SLAG BLASTING
ReplyDelete